E-Space Facility: Arlington Municipal Airport

Project Overview

Lindamood performed site preparation and mass earthwork for the E-Space Facility at Arlington Municipal Airport in partnership with MOSS & Associates. All work was executed within an active municipal airport environment, requiring strict safety compliance and operational coordination.


Scope included implementation of SWPPP measures, approximately 130,000 cubic yards of cut-to-fill and stockpile operations, 230,000 cubic yards of moisture conditioning, and installation of 70,000 tons of flex base.


Key project elements included:

  • Earthwork within an active airfield environment

  • 130,000 CY cut-to-fill and stockpile operations

  • 230,000 CY moisture conditioning

  • 70,000 tons of flex base installation

  • SWPPP implementation and regulatory compliance

  • Sequenced operations under airfield access constraints


Execution demanded disciplined logistics, continuous coordination with airport stakeholders, and strict adherence to operational and safety requirements. The project reinforces Lindamood’s ability to deliver complex earthwork programs within regulated aviation environments while maintaining schedule alignment and operational continuity.

Client

Moss & Associates, LLC

Location

Arlington, TX

Duration

Market

Aviation